Use automatic goal-based acceleration to define the acceleration target and let Acumen 360 automatically generate the schedule scenario that meets that goal.
To define an acceleration goal for a specific activity, complete the following steps:
-
Select the S4 // Acceleration tab.
-
In the Acceleration menu, click
Accelerate Schedule.
-
On the Accelerate Schedule dialog box, in the Schedule Accelerator group:
-
Select the Accelerate Activity tab.
-
Click
Select / Change Activity to Accelerate to select the activity against which the acceleration needs to be conducted (for example, accelerate completion of construction).
-
Use the goal options (date field or sliding scale) to set the target goal for the activity acceleration.
-
Click
OK to run the simulation.
-
Compare the results using forensics, timeline, and analysis views.